Dear Gurus,

We are doing STO with account assignment category Q (Moving project stock from one plant to another plant, same company). After posting delivery stock goes to in-transit.
Here if we check in MB52, stock is showing in-transit but not showing any value (zero).

Is this standard behavior Or any customization to be made to show the value.
To verify the concept in manual movements (303, 305), test case cannot be preferred due to split valuated materials.

Need your advice.

Thanks

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Jürgen L
Jun 11, 2017 at 09:39 PM
0

can you show a screenshot of your accounting documents which are created for your goods issue?

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Dear Jurgen,

Thanks for your quick response.
Please verify below accounting entries for project related stock (641 movement).
If the below details are not suffice, Kindly specify what columns are required.

Thanks

0
Vjay SAP Jun 15, 2017 at 05:27 AM
0

Dear Gurus,
Please suggest..

Share
10 |10000 characters needed characters left characters exceeded
Ken Melching
Jun 23, 2017 at 12:20 AM
0

That sounds right since you are moving the stock within the same company code. Inventory value is held on the balance sheet and since you are not changing company codes the value is not moving.

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Ken Melching,
Stock in transit value is showing for normal stock(t-code: MB52). But for project stock, value is showing as zero.
Please suggest.

Thanks.