Dear Gurus,

I have problem in Project system, wherein by mistake i have selected customer project profile instead of Capital Investment Project profile.

I have incurred some costs in Network alread in this project & posted.

I am not able change the CJ07 the project profile from Customer Project to Capital Investment, due to which the costs booked already in Network are setting in Network and not able to CJ88 from Network to WBS from WBS to AUC.

I have changed the CJ12 the WBS element from customer to capitable investment, but not able to change the project profile in Project Definition level.

Kindly help if u have any solution.

Thanks in advance

Srihari Ediga