dms-work-order.jpgdms-notif.jpgDear Experts

I am going to configure DMS in one of our Client SAP system. We'll be using Content Server for this project. My first task is to create links for Work Orders and Notifications.

I have a reference system from another project where DMS is already configured. I am attaching one screenshot from Work Order, where the screen for DMS link is given. But I am unable to figure out whether any screen enhancement is used or some Standard functionality.

Could you please help me out with that? Your help would be highly appreciable. Please find the attachement for reference.

dms-work-order.jpg (177.3 kB)
dms-notif.jpg (77.7 kB)
10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
K Jogeswara Rao Jun 09, 2017 at 05:27 AM
0

Both screens are standard configuration only.

For Notification

the DMS screen you posted adds when you add screen area 092 (DMS links) to any tab in SPRO.

For Order

Here also the picture you posted comes from standard. This is activated from EHP7 Business functions. For this the following Business functions need to be switched on.

  • LOG_EAM_OLC
  • LOG_EAM_CI_6
  • LOG_EAM_SIMPLICITY
  • LOG_EAM_SIMPLICITY_2

In your case because you have done this, you are having this screen.