mrp type V1 and strategy 20

Jun 08, 2017 at 10:59 AM

62

avatar image

Hİ Gurus;

I have a scenario.

FERT str:20

ROH mrp type V1

ROH Maximum stock level:1000 Reorder Point:100 ROH stock:110

customer order:100

When I run MRP, for my ROH does not cosider customer order. Can you help me for that?

I hope I can explain myself clearly.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Caetano Almeida
Jun 08, 2017 at 06:05 PM
0

Hello

MRP should generate a planned order to cover the sales order requirement. Then the BOM is exploded and dependent requirements are generated for the raw materials.

However, if you are using a reorder point MRP type, dependent requirements are not considered. With reorder point, replenishment will be triggered whenever the stock falls below the reorder point, so the dependent requirements are not relevant.


Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Thank you Caetano.

If dependent requirements are not considered, how will my raw materials be consumed? How will it fall down? Sorry I didn't get it.

Thank you in advance.