Hello,

( a) I want to do a cost center check in SES without affecting release strategy. Which exit to use ?

(b) With the exit SRVREL, I'm able to do the check, but it deactivates the release strategy. Is there anyway to have activate release strategy when SRVREL is used for cost center check ?

(c) I have also used the exit SRVESKN, but it gets triggered before the screen entry of the cost center. How can I make it trigger after screen entry of the cost center ?

Thanks & regards,

Sheeja.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Sheeja,

Just check the Release strategy.. for Service entry

SPROMM-Ext service Mgt--Define Release procedure

Here in chek what are the Release Indicators you r using ..i mean there are some 6 indicators...

and Then check the Release strategy...here check the Release status in Details of each strategy...and for the last level of release check what is the release indicator....

because if the changebility indicator is 2:Changeable, no new determination of strategy ...then no new strategy will be determined..

Just chck

Regards

Vikrant............

Former Member
0 Kudos

Hi Vikrant,

The problem of deactivation of release strategy occurs when we activate the user exit SRVREL for some checks. How to have an active release strategy after activation of the above exit.

Thanks.