request for production

hi

when we doing availability check if no requested quantity is not available. how the production order is raised ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Mar 29, 2007 at 05:39 AM

    hi,

    it depends on your mrp type and stratergy group settings which triggers PO with the help of requirement class.

    this also requires pp customising for PO doc type and plant assinment for PO doc type .

    reward if helps !!!

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      hi

      thank you vary much for your answer. Is availability check is possible without TOR.

      if possible how ? could please explain it.