Hours spent on a WBS

Former Member
0 Kudos

HI all,

My company wants to input Hours spent by month somewhere in the WBS master record. Do you know where this can be done? I will also need 2 more fields where I can enter the Employee name and an ID.

Any help will be appreciated

thanks

Brian

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Try OPS1, there are 6 fields you can use. They can be the type of text, quantity, date, and value.

Enter then this user defined fields to projet prfile OPSA...

Standart SAP explanation:

There are the following user-defined fields, defined in the R/3 System:

General text fields

You can use these fields to enter your own data, for example:

information on people responsible

information on substitutions/proxies

internal phone numbers

quantity fields and their units

You can also define formula parameters for quantity fields. The formula parameters are used in for example, work center formula calculation or network costing.

Value fields and their units

Date fields

You can use these fields to enter internal start data, for example.

Checkboxes

Here, you can enter information for analyses in the Information System.

The key words for the user-defined fields are determined by a key word ID.

Further notes

Please note that the contents of user-defined fields is not checked by the SAP System.

You can make your own enhancements (i.e. customer-specific functions) to the user-defined fields.

The enhancement CNEX0001 is available for you to do this in development class CN (application development R/3 PS Project management). Create a check of user-defined fields