Landscape for Urgent Correction

Former Member
0 Kudos

Hi all,

I am working on Urgent Correction process PoC. I have created a logical component with multiple clients (two quality clients, two integration clients) between development and production client.

When I created an Urgent Correction change document (SDHF) with the above mentioned Logical Component, I could see only three clients (dev, quality, and production) not all the clients?

When I used same logical component for Implementation Projects, I could see all the clients..

Could anybody explain why Solution Manager behaves differently for Urgent Correction (SDHF) and Normal Correction (SDMJ) even though the same logical component is used. Please make a note that I am working on PoC.

Response is greately appreciated.

Mike.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

When you create the Urgent Correction change document (SDHF), you select the project.

At this point, The system search the right Logical component.

Another interest think is this

if your Logical component has 4 systems for example.

DEV - INT - QAS - PRD

but you have 2 routes defined in the STMS like

Route 1 : DEV - INT - QAS - PRD

Route 2 : DEV -QAS -PRD

This Urgent correction take the shortest route..(Route 2).

If you have another doubt, chat me!!!

Wen

MSN; wenceslao@hotmail.com

Solution Manager Consulant

Former Member
0 Kudos

Hi Wen,

Thanks for the response. So in that case, could we use two separate Logical Components for each scenario (Urgent Correction & Normal Correction)?

Regards,

Mike.

Former Member
0 Kudos

Hi Mike,

With Urgent correction it will choose the startest path as told by wen.So when you move the tp to quality,it will move to only one of the client which is in the shortest path.For other clients you need to exexcute a report /TMWFLOW/SCMA_BTCH_SYNC_TEST.When you execute this report,it will ask for the source client to which the tp is already moved and the target client were you want to move it.This report can be set to run in background at regular intervals so that wheneevr you move to quality in urgent correction,this report takes care to move the tp across other clients also.

Thanks and regards,

Avinash.

Former Member
0 Kudos

Avinash,

What happens if we want to import into multiple systems/clients? What are the advantages of this approach?

Is there any way that we can configure the TMS to reflect the desired path?

Thanks,

Mike.

Former Member
0 Kudos

Hi Mike,

If we want to import to multiple clients/systems we need to include them in the system landscape under quality system.(even the integration clients should be included as quality system in system landscape).

The task list of an urgent correction contains exactly one production system (where the problem occurred) and only the systems that are on the shortest transport route from a development system to the production system. The reason for this is that you want to implement your urgent correction as quickly as possible.

So when we use Urgent correction the only option available to move the tp's across multiple clients is to use the report.

We have also tried to do some setting in STMS but ended in Vain.

Hope this information is useful.Please revert back for any clarification.

Thanks and regards,

Avinash.