Cproject -> PS replication. Problem

35 Views

I have the following task: create a structure of the existing cProject project in the PS.

New project type is defined for automatic (on save event) WBS elements integration. I have checked the multilevel automatic controlling either for project element or for project structure in controlling scenario, but after I push "Save" button in cProject at Accounting bookmark WBS elements aren't created automatically, I may do this only manually using the existing PS project.

If I selected internal orders instead of WBS - everything was OK.

Do you have any idea what is the reason?