PS Project creation from PPM Project

Former Member
0 Kudos

Hi

My client want to create PS project from cProjects (as replication).

They don’t want to use Project profile as CPR1 as they have their own project profiles defined.

Project Profile will be selected base on custom/standard field of PPM project.

And some 5 attributes also need to be transferred from PPM to PS while creation.

Also they want automatic link between PS WBS and PPM tasks

Can you please suggest some BADI ?

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member185558
Active Participant
0 Kudos

Hi Nitin,

By default we are using project profile CPR0001(you can check this in IAOM0 transaction)

Now if we want to use different project profile

We need to implement BADI

AOM_BUSINESS_SCENAR with Method CHANGE_PROJECT_PROFILE

In this method you can code which profile to be used based on business rule.

Thanks and regards

Niketan