PS Project creation from PPM Project

Hi

My client want to create PS project from cProjects (as replication).

They don’t want to use Project profile as CPR1 as they have their own project profiles defined.

Project Profile will be selected base on custom/standard field of PPM project.

And some 5 attributes also need to be transferred from PPM to PS while creation.

Also they want automatic link between PS WBS and PPM tasks

Can you please suggest some BADI ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 05, 2017 at 07:15 PM

    Hi Nitin,

    By default we are using project profile CPR0001(you can check this in IAOM0 transaction)

    Now if we want to use different project profile

    We need to implement BADI

    AOM_BUSINESS_SCENAR with Method CHANGE_PROJECT_PROFILE

    In this method you can code which profile to be used based on business rule.

    Thanks and regards

    Niketan