Changing item category when inserting task list in order

Hi

we got an requirement where we need to change the item category of material when inserting the task list in work order. we have used the BADI IWO1_Integration2 which actually converts into N , but purchasing data tab is not created .

when we tried to input material directly in work order it worked

any suggestion

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jun 01, 2017 at 06:59 AM

    IN BADI IWO1_TL_INTEGRATION2,which fields are you changing in C_RESBB?

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Pete

      after populating the following fields purchasing tab got created

      Account assignment indicator

      Direct procurement indicator

      small clarification , whether we have to still pass the remaining purchasing data like purchasing group, cost element, material group from BADI OR if we maintain these values in profile for external material whether it will copy

      Regards

      Thyagarajan

  • avatar image
    Former Member
    Jun 01, 2017 at 04:43 PM

    Hi Pete

    we are changing only the below fields

    POSTP , CHARG and tried to populate the KNTTP (Account assignment category)

    is there anything to be added

    Regards

    Thyagarajan

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 02, 2017 at 06:33 AM

    Thyagarajan

    Why are you changing KNTTP?

    It looks like there are qute a few oher fields you need to populate..

    The best thing to do is create an order and add the same material twice, one where POSTP=L and one where POSTP=N, then save th order.

    Then go to RESB via SE16 and check the differences between thes two records.

    Ensure you copy these differencs to C_RESBB.

    PeteA