on 03-15-2007 1:50 PM
Dear all,
When testing the datasource 2LIS_05_QVDUN, it appears that the inspection lot without decision usage are not extracted (only the inspection lots with status equal to 5 are been taken into account).
Is there a solution to extract the inspection lots without decision usage ?
Thanks a lot for your help.
Michel.
You should check the docs as they state:
<i>Data extraction only takes place for inspection lots once the usage decision for an inspection lot has been made</i>
So the behaviour of this extractor is correct (unfortunately in this case)
Message was edited by:
Pabloj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Pabloj for your answer.
I try to create a generic datasource which use the delta queue through the Business Transaction Event. Unfortunately, find no business event for the creation or the change of an inspection lot.
May you have any idea how to deal with or any solution to extract through a delta process all the inspection lots without any regard to their decision usage status ?
Regards, michel.