I know PP/DS plans at storage location level within a plant, but do SNP plan at storage location level too?
Thanks
Mono
<b>Re: Mapping ATP categories</b>
Hai Mono,
As far as I know, SNP can plan at Storage location MRP area level. I am not sure whether it can plan at storage location level, if we do not configure MRP area.
Regards,
Murali.J
<b>Re: Mapping ATP categories</b>
Murali has answered your question. Storage location in R/3 needs to be assigned to a MRP Area. This MRP Area when transferred to APO becomes a separate location (Type 1007) with its own location-products. Then you can run SNP or PPDS planning at that location without any issues.
Thanks,
Somnath