Hi,

I want to schedual a job with the following condition.

The job must be execute only at the last 3 days of the current month & at the first 3 days of the next comming month....

i.e: 28/03/07 to 03/04/07

Need your help....

Regards,

Neehir Bhatt

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

there are following options to schedule a job,

hourly, daily, weekly, monthly and other period. in other period you can specify month, week, days etc..

alternative for you is schedule the required jobs for monthly basis.

cheers,

-Sunil

Former Member
0 Kudos

Hi,

your answer is the default answer, that I know... is there anything else from which we can get the desired output..???

Regards,

Neehir Bhatt

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

As Ed indicated, you can do this in SAP CPS Calendars.

You need to create a time window with two elements, using the "Advanced" option in the element:

- one for the last three days in the month (using the "last day in month" function)

- one for the first three days in the month (using the "day in month" function)

In both cases you can specify a range of days to be included.

Regards,

Anton.

Former Member
0 Kudos

Hello Neehir,

Your requirement is partially possible in standard SAP but you need to to this activity everymonth.

What you can do is say on 28th of a month you create a job with periodicity daily. Then in scheduled start you can give 28th of the current month with the time. Then in No start after you can give 3rd of next month with the time of the run.

But then this activity will have to be done on monthly basis.

May be it is possible through third party SAP job scheduling tools like Redwood,UC4 etc.

Please award points accordingly.

Regards.

Ruchit.

Former Member
0 Kudos

Hi,

your answer is the default answer, that I know... is there anything else from which we can get the desired output..???

The idea about the 3rd party software is good....

Regards,

Neehir Bhatt

ed-holland
Explorer
0 Kudos

With SAP CPS calendaring functionality, this can be done.

- Ed

Former Member
0 Kudos

you can do this thing with the factory calander.

SAP Factory Calendar -

Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.

you can get more help in:

[https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/97d2e8b3-0b01-0010-b787-b8ce558a51c2|https://www.sdn.sap.com/irj/sdn/go/portal/prtroot/docs/library/uuid/97d2e8b3-0b01-0010-b787-b8ce558a51c2]

in transaction RSPC you can schedualing job and use the calendar in the start process chain.

Former Member
0 Kudos

I doubt this could be done with standard features, you really might want to check the third party tools available for this. Naturally, I'd recommend you'd try [BatchMan|http://honico.com/content/EN/batchman.html] in which this could be done very easily, but I can't speak for the other tools.

Former Member
0 Kudos

Hi Björn,

Rest assured, there is no doubt that the calendar requested here can be achieved with standard SAP CPS functionality. I'm sure you understand that I am absolutely sure of that :-).

Kind regards,

Anton Goselink

Former Member
0 Kudos

Hey Anton,

thx for clarifying that!