Dear gurus,

I try to use LTMC/LTMOM to migrate BOM to S/4 HANA op1610. But I found below issues:

1, one material can only input one BOM. If I have alternative BOM, System can only upload the last one.

2, If a material already have a BOM, it is not possible to upload alternative BOM.

3, I found it had a parameter in target structure (LTMOM), eg. FL_BOM_CREATE, FL_NEW_ITEM. But I did not know how to use these functions.

4, One project seems can only used one time, because when you get an error in a try, you cannot revise your data source and do it again. the error message cannot be removed.

Thanks for all your advice in advance.

B.R.

Sivan

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Jul 28, 2017 at 03:41 PM

    I have the same problem, the alternatives weren't created. Do you already know how to solve?

    Thanks in advance,

    Cristina Aleixo

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Sep 25, 2017 at 11:39 PM

    Same problem here. I think it could be something with BAPI CSAP_MAT_BOM_MAINTAIN.

    Thanks.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 24, 2017 at 09:42 PM

    It is by design, see OSS 2545698