on 05-31-2017 6:38 PM
In the service order processing, activity type that will be assigned will use unit of measure AU and not H (hour). Been trying to test AU but system is still throwing error "please enter unit of time". Wanted to use AU since the operation will be task-based rate and not hourly rate. Any help will be greatly appreciated.
This is standard behaviour - all UoM for the operations and confirmations must be time based.
One trick I have used a few times in the past is to create a new UoM (TCode CUNI), say "ZAU", but give it a time dimension similar to "H". You will then be able to use "ZAU" in your operations and time confirmations.
PeteA
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Peter. That is exactly what I did and it worked!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
94 | |
11 | |
9 | |
5 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.