Hi,

We have an issue with an Engineering Record that has a Task that has been executed then no one else can pick it up or forward onto anyone else .Normally a 'substitute' would of been setup to handle in this situation.... but the user had not set one up.

We need to either get a substitute setup behind the scenes or find some way to flag the task as not grabbed. e.g cancel the assignment, or find some other way to say it has been completed so that we can continue the process route for authorisations.

Is this possible?

Regards

Gary Bracegirdle

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Jun 05, 2017 at 08:14 PM

    Hi Gary

    You can simply complete the task in admin

    Transaction SWIA

    activity area SCMG,type PLM_SCR

    Thanks and regrds