Hi Experts,
we have noticed a strange behavior in one of the maintenance plan,the maintenance plan is created on 2009,it is working fine but all of sudden for the call object is on hold for call date 15.07.2017.schedule on hold not calling the call object.
scheduling indicator-Time key date,call horizon is 100 %,scheduling period is 24 Month,IP30 run every fortnight for 45 interval days for call object.Please help me in this regard.
It is a single cycle plan with frequency 1 Year.
Is the Completion Requirement flag set in the maintenance plan?
If so, then ensure that the orders for the previous call are all TECO.
PeteA
Completion Requirement flag is not set
Start of cycle date is -15.07.2009 and it is greater than task list validity date,it was working fine since long all of sudden it is not not call the call object for plant date-15-07-2017.
Completion Requirement flag is not set
Start of cycle date is -15.07.2009 and it is greater than task list validity date,it was working fine since long all of sudden it is not not call the call object for plant date-15-07-2017.
Can you send some screen-shots including the algorythm for the call that is causing the issues.
PeteA
schedule-hold.pngalgothrim-screen-shot.pngscheduling-parameter.png
Please find all the attachments.
Try going into IP10 and pressing the rfresh button at the bottom of te screen to see if that updates the data
PeteA
i even tried that in IP10 ,update scheduling button,it is not working .
Are there nay error messages in the IP30 log?
Also try the following:
.
PeteA