Update of Network Activity cost to Cost Element

I have created a Project With Network activities, the network activities have material component based on which reservations are automatically generated. Conceptually the planned cost should be copied to Cost Element. But the planned cost is not getting copied to cost element. I need to copy the planned cost to SAP PPM. And also i need to make Earned Value analysis. Kindly help me.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Jun 01, 2017 at 08:47 AM

    To reflect stock planning you will need to have a valuated project stock on your project.

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 07, 2017 at 01:09 AM

    What project stock is your project, valuated or non-valuated? Paulo is correct.

    For non-valuated you will need to use a Cost Network Activity.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Oct 31, 2017 at 10:41 AM

    Hi Ken,

    We are using Valuated Project Stock

    Add comment