I have created a Project With Network activities, the network activities have material component based on which reservations are automatically generated. Conceptually the planned cost should be copied to Cost Element. But the planned cost is not getting copied to cost element. I need to copy the planned cost to SAP PPM. And also i need to make Earned Value analysis. Kindly help me.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi Ken,

We are using Valuated Project Stock

kenmelching
Active Contributor
0 Kudos

What project stock is your project, valuated or non-valuated? Paulo is correct.

For non-valuated you will need to use a Cost Network Activity.

Paulo_Vitoriano
Active Contributor
0 Kudos

To reflect stock planning you will need to have a valuated project stock on your project.