Hi,

I am using multiple start process steps, using a fork in BPM. Hence i have the same correlation name being used in both the Receive steps. However i am getting the message Correlation <correlation name> already in use message when i try to activate.

Any reason for this ?

Regards

Ganesh

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Mar 13, 2007 at 05:51 PM

    u need to use different coorelation id for the second recver inside bpm.....<b>uniqueness</b> is the key point

    refer:

    Checklist" target="_blank">http://help.sap.com/saphelp_nw2004s/helpdata/en/6d/94364296f1b26be10000000a155106/content.htm">Checklist: Making Correct Use of Correlations