Skip to Content
0

Strategy group for MTS scenario

May 30, 2017 at 11:59 AM

101

avatar image

Hi,

Which strategy group should I use for make to stock scenario in material master. So that I will get the WBS element in planned order as well as in production order. I have tried with 51 strategy group but I am not getting WBS in Planned order(PS - PP integration).

Kindly help me to resolve this issue.

Regards,

Ramesh

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

Sunil Yadav Jun 02, 2017 at 06:14 AM
0

Hi Ramesh,

Check below link for understanding:

https://blogs.sap.com/2013/12/07/make-to-stock-strategies-strategy-10/

thanks

Sunil

Share
10 |10000 characters needed characters left characters exceeded
Ramesh kumar Jun 07, 2017 at 05:12 AM
0

Hi Sunil,

Thanks for the reply.

I have checked the same but , also I have assigned the same material to my network then run MRP. There are not any WBS copied into planned order.

I have also done the same thing for make to order production/project scenario used strategy group 21, working fine.

I need to have link between PS and PP. I need to do same thing for MTS scenario.

Kindly suggest how can I link so that I can get WBS in planned order or production order.

Regards,

Ramesh

Share
10 |10000 characters needed characters left characters exceeded
Sunil Yadav Jun 08, 2017 at 05:36 AM
0

Ramesh,

this might be due to some missing config issue. you need to check config for strategy.

thanks

Sunil

.