Hi all,

This relates to <b>direct procurement</b>(classic scen).

I have created local Porgs and PGrps and also backend Porgs and PGrps.Proper categories have been assigned and PO is also created.

My question is:PO is created in SRM system with the local POrg and PGrp.When PO is replicating to back end.....

..

a.]how will the system know which POrg and PGrp is to be picked for back end?

b.]Say,we have 2 POrgs and 5 PGrps....and PO created belongs to one POrg and a PGrp.Do we have to create all POrgs and PGrps in the organization and link it to backend in function tab?

c.]Is there a BADI to be used for mapping?Which one?

d.]Any changes that are to be made in PO should be made in SRM PO.Now how will those changes reflect to the already replicated PO in R/3?Any background job that does the changes?

<b>Extended classic scenario</b>

Once PO is created and when it has to be replicated to back-end(SAME QUESTIONS)

a.]how will the system know which POrg and PGrp is to be picked for back end?

b.]Say,we have 2 POrgs and 5 PGrps...do we have to create all POrgs and PGrps in the organization and link it to backend in function tab?

c.]Is there a BADI to be used for mapping?which one?

d.]Any changes that are to be made in PO should be made in SRM PO.Now how will those changes reflect to the already replicated PO in R/3?Any background job that does the changes?

Please share your views.Points will be awarded.

Many thanks

Trey

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • avatar image
    Former Member
    Mar 12, 2007 at 06:56 AM

    Hi,

    c.]Is there a BADI to be used for mapping?Which one?

    Try BADI "BBP_PGRP_ASSIGN_BADI".

    d.]Any changes that are to be made in PO should be made in SRM PO.Now how will those changes reflect to the already replicated PO in R/3?Any background job that does the changes?

    Jobs BBP_GET_STATUS_2 AND CLEAN_REQREQ_UP need to be scheduled in background for classic scenario in addition to your distribution model.

    HTH.

    BR,

    Disha.

    Pls reward points for useful answers.

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 12, 2007 at 07:11 AM

    Hi

    a) Backend Purch.grp/org is determined by number of ways:

    - Maintain a purchasing group for parameter EKG in backend RFC user parameters in transaction SU01. Purchasing organi-zation is determined based on the plant.

    - Use backend purch.grp/org while creating SRM PO

    - Use User Exits in BAPI in R/3. Set the purchasing group in the user exit in BAPIs BAPI_PO_CREATE1 (EXIT_SAPL2012_001 and EXIT_SAPL2012_003) and BAPI_PO_CHANGE (EXIT_SAPL2012_002 and EXIT_SAPL2012_004).

    b) If you want the SRM POs in the backend to be created with different purchasing groups and purchasing organizations, suggest you to create them in SRM also and use them while creating PO.

    c) see (a) above

    Best regards

    Ramki

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 12, 2007 at 08:20 AM

    Hi

    Which sRM version have you implemented ? Which Scenario are you using ?

    Here are the possible answers

    <u>Classic Scenario -></u>

    a) Purchasing organi-zation is determined based on the plant.

    b) Maintain the same POrg as well as the PGrps data using configuartion, both in SRM as well as the R/3 system in order to miantian consistency.

    c) I guess, BADI is not required here.

    d) Execute reports - BBP_GET_STATUS_2 AND CLEAN_REQREQ_UP. Schedule these report as Jobs using SM36 transaction, to need to be scheduled in background for classic / extended classic scenario.

    <u>Extended Classic Scenario -></u>

    a) The Leading PO created in SRM will contain all the Porg / Pgrp details, which will be replicated to R/3 PO.

    b) Maintain the same POrg as well as the PGrps data using configuartion, both in SRM as well as the R/3 system in order to miantian consistency.

    c) Try the following BADIs using Se18 Transaction.

    BBP_PGRP_ASSIGN_BADI                 EBP Purchasing Documents: Assign Purchasing Group(s)    
    
    BBP_PGRP_FIND                                        Shopping Cart: Determine Responsible Purchasing Group(s)

    d) Execute reports - BBP_GET_STATUS_2 AND CLEAN_REQREQ_UP. Schedule these report as Jobs using SM36 transaction, to need to be scheduled in background for classic / extended classic scenario.

    <u>Please understand the details of direct procurment as well by referring to the following links -></u>

    http://help.sap.com/saphelp_srm50/helpdata/en/d9/12f33901fe874ce10000000a114084/frameset.htm

    http://help.sap.com/saphelp_srm50/helpdata/en/b7/15d4396898042fe10000000a114084/frameset.htm

    http://help.sap.com/saphelp_srm50/helpdata/en/6a/4b9e3b891da20ee10000000a114084/frameset.htm

    http://help.sap.com/saphelp_srm50/helpdata/en/38/39d03bcf36d137e10000000a114084/frameset.htm>

    Hope this will help.

    Please reward suitable points, incase it suits your requirements.

    Regards

    - Atul