Hi all,

This relates to <b>direct procurement</b>(classic scen).

I have created local Porgs and PGrps and also backend Porgs and PGrps.Proper categories have been assigned and PO is also created.

My question is:PO is created in SRM system with the local POrg and PGrp.When PO is replicating to back end.....

..

a.]how will the system know which POrg and PGrp is to be picked for back end?

b.]Say,we have 2 POrgs and 5 PGrps....and PO created belongs to one POrg and a PGrp.Do we have to create all POrgs and PGrps in the organization and link it to backend in function tab?

c.]Is there a BADI to be used for mapping?Which one?

d.]Any changes that are to be made in PO should be made in SRM PO.Now how will those changes reflect to the already replicated PO in R/3?Any background job that does the changes?

<b>Extended classic scenario</b>

Once PO is created and when it has to be replicated to back-end(SAME QUESTIONS)

a.]how will the system know which POrg and PGrp is to be picked for back end?

b.]Say,we have 2 POrgs and 5 PGrps...do we have to create all POrgs and PGrps in the organization and link it to backend in function tab?

c.]Is there a BADI to be used for mapping?which one?

d.]Any changes that are to be made in PO should be made in SRM PO.Now how will those changes reflect to the already replicated PO in R/3?Any background job that does the changes?

Please share your views.Points will be awarded.

Many thanks