IW81 Automatic creation of operation offsets

May 29, 2017 at 06:10 PM

56

avatar image

Hi experts.

In Plant Maintenance when IW81 is used to create a refurbishment order with multiple operations, no offsets are automatically created between the operations. When IW31 is used to create a regular maintenance order, the operation offsets are automatically created using a default of 48 hours.

Is there a way to make IW81 behave like IW31?

IW81 Screen Print

IW31 Screen Print

Thank you.

Joseph

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Joseph Soltys Jul 14, 2017 at 11:24 AM
0

Found a work-around. IW81 can be used to create the refurbishment order without offsets. Then by editing and saving the order using IW32 the necessary offsets will be created.