We are setting up outline agreements with item category D. We specify the service master numbers on the Service tab, with the pre-negotiated price for each service. I have checked the "Price change in entry sheet" to ON for a few services.

We create the PO as a blanket amount. On the Service tab, we do not list the services. On the Limits tab, we list the overall limit amount, and enter the outline agreement number. When we enter the SES, the prices are pulled from the outline agreement, and cannot be changed. This is what we want for most services, except for those that I turned the Price Change to ON. Is it possible to make the Price Change in SES indicator work on the outline agreement?

Accepted Solutions (1)

Accepted Solutions (1)

Ramki
Active Contributor
0 Kudos

Hi Jen

By just selecting 'price change allowed' indicator in Contract will not serve your purpose.

While defining 'Limits' in PO, there is a 'Price change in entry sheet allowed' indicator in 'Contracts' tab. You select this indicator. You can also include your contract there.

I am sure it works.

Best regards

Ramki

Answers (1)

Answers (1)

Former Member
0 Kudos

My requirement includes that the "price change allowed" indicator is checked by default as soon as the PO is created from PR in batch mode. Also, how do I achieve this in POs that have already been created.