Hi All,

Can u pl let me know how to ensure to get BS Element in CB level, as except BS element every detail given in Network ie., procurement of materials or Procurement of services are flowing as per the POs

Request pl help to set the same enable me to get BS element at CB.

PS Process at my end is

1. PRoject Definition

2. Include WBS Elements

3. Create Network and assign WBS Element

4. Create PR- materials & PR-Services in Network ; External processing.

5. PO is made against the PR

Hope the above is suffice to give a solution.

Thanx in advance

Regards

Srihari Ediga

Accepted Solutions (0)

Answers (1)

Answers (1)

former_member221039
Active Participant
0 Kudos

no one responded & hence closed