maintenance plan using cycle sets is it possible to use more than one equıpment.

May 26, 2017 at 08:07 AM

80

avatar image

maintenance plan using cycle sets, can we use more than one counter which are belong different equipments. one plan ,more then one item.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Paul Meehan
May 26, 2017 at 01:47 PM
0

Hi,

The cycle set itself does not reference any particular equipment. However when you create the plan only one reference object can be specified per maintenance item. You can have multiple maintenance items in the plan (for same or different equipments) but all items will reference the same cycle set*.

*You can split the overall cycle set into cycle set sequences. Individual maintenance items can then reference a particular sequence (subset of the cycle set) only.

-Paul

Show 3 Share
10 |10000 characters needed characters left characters exceeded

Thank you Paul.The answers is what I just want to hear.One more comment,I understood that I can use only one counter for one maintanence plan,wherter plan is multiple counter or not.

0

If you have defined a multiple counter plan then more than one counter can be used

0

Thanks Paul

0
Peter Atkin May 26, 2017 at 02:25 PM
0
Share