Hi All,

What are the advantages of going for BI QAS system refresh from the production client. Since all the data lies on our r3 source systems (PRD & QAS), what all would be changed in our BI QAS box when we go in for a BI system refresh!

Thanks,

Antarpreet

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Correct if its R/3- ECC Prod to QA refresh,You would do that so that you have perfect real time scenario data for running test scripts in other words to do carry out proper functional testing.

BI Production to QA refresh to create a non-productive system landscape for testing, quality assurance or other purposes. Or you want to copy your productive landscape onto a new productive landscape to change some property of the systems like hardware, operating system or database.Also to test some proof of concept like NW2004s ,but scenario like POC(proof of concept) would be done in Sbox/Dev(Copy of Prod) and upgrade Sbox or Dev to QA and PRD.

The SAP BW system is refreshed without refreshing the Source System in

parallel. The following implications should be understood:

1)SAP BW Objects (in SAP BW and Source System) need to be re-synchronized

2)All data will be out of synchronization between SAP BW and Source Systems

3)Master, transactional, and global settings data re-synchronization is required.This effort can be considerable.

4)SAP BW is essentially an “island” until data is re-synchronized

5)SAP BW systems with multiple Source Systems may want to consider using the InfoObject 0LOGSYS in data models as it provides an easier mechanism for selecting data during Data synchronization

Hope it Helps