on 03-05-2007 6:28 PM
can any one tell abt DETERMINE_DUE_DATE FM and tell me how to calculate due dates
Hi,
The payment due date isn't stored in a SAP database table - instead it is dynamically calculated every time you run a report.
The function module available for calculating net due date is DETERMINE_DUE_DATE.
It can be calculated via baseline date and payment terms. Baseline date is stored in RBKP table (RBKP-ZFBDT).
Regards,
Ferry Lianto