HALB Date Divergence in MRP Processing

I have a FERT material. Inside this material I have a HALB that inside it there is a ROH. The FERT has the date of release of the OP for 03/08/17. The HALB will be consumed in this PO on 07/08/17. This HALB is indicating in the MRP processing that the date of need is 07/12/17. Only this is not the date of need, but the day 07/08/17. The day 12/07/17 would be the day that by the term of delivery I should release the requisition so that the ROH material arrives on 07/08/17. Does anyone know what I should do to make the HALB date the production order need date?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 30, 2017 at 06:44 AM

    Please check the planned delivery time, schedule margin key values of the HALB, whether they are correct?

    Hope by rectifying the same, the issue may resolve.