Connecting BI to different ECC clients

17 Views

Requirement is to connect BI client to two different source systems i.e. Dev and Test. I know we can connect BI to multiple ECC(R/3) clients...

1. I would like to know the <b>technical steps</b> to connect BI to Test client.

2. To Load current objects in BI from Test instead of DEV.

What changes do I need to make for my objects like DTP's, Infopackages etc.

Currently all DTP's and Infopackages are pointing towards DEV client. Do I

need to create new DTP's and Infopackages objects.

NOTE: TEST box is not in the transport landscape. It is only created and loaded with data for user testing.

Once user's complete testing, we will disconnect test connect and start transporting objects from DEV - QA - PROD.

Please advise.

Thanks,

BI

Message was edited by:

B I