Former Member
Mar 02, 2007 at 04:23 PM

Required Delivery Date vs. Schedule Line Date vs. Calendar

306 Views

Hello Experts,

The Factory Calendar shows that Monday to Friday are the only working days. Now, the user created a sales order and manually entered a date that falls on a saturday. As a result, the schedule line dates were all set on saturday. Availability check is in place and stocks are available.

My question is: Why did the system proposed saturday as the schedule line date when the calendar shows saturday is not a working day? Am i correct to conclude that the manual entry in the required delivery date in sales order is the priority in determining schedule line date? Your inputs on this scenario would be highly appreciated.

Best Regards,

Gene