Skip to Content

After MRP run

All,

Suppose a new material is there .

No info record is there for this material.

Never created a PR and .

For this material after MRP run , if PR is generated , whether valuation price will come in the PR ?

Kindly advise.

regards,

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Mar 01, 2007 at 08:22 PM

    Hi Sandeep,

    The valuation price for PR will be taken from Material master for that particular material.

    regards

    Anand.C

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Mar 05, 2007 at 01:54 PM

    Hi Sandeep,

    If you have not maintained info record & you have not entered proce in accounting view of material master,after running a MRP system will show you the zero price in PR.

    The valuation price for PR will be coming from Material master,if info record is not there..

    Hope it will help you.

    Regards,

    Manish Agarwal

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.