I setup a milestone billing plan and it is working properly. My problem is the first invoice contains the quantity. This makes is look like we billed the full quantity on the first milestone date. Both our accounting department and demand planning department do not like this. They would prefer that the quantity be included on the last billing date.

I think this is standard and I don't think this is possible because there's probably a divide by zero restrictions elsewhere in the system. Does anybody else have this problem and how did you overcome it?

Thanks

Tom

Accepted Solutions (0)

Answers (1)

Answers (1)

Jelena
Active Contributor
0 Kudos

Google -> milestone billing quantity site:sap.com -> this post -> this note

If you do multiple deliveries with partial quantity then you can implement the suggestions in the note. In other scenarios I don't believe it's feasible but then I also don't see what would be a valid business case and how it could even possibly be expected to look.