cancel
Showing results for 
Search instead for 
Did you mean: 

Network Planned Costs in PS

shabbir_ahmed2
Explorer
0 Kudos

HI ALL

when i planned the network activity cost in project system then system also assigned that amount against the budget ....so my avable budget is reduce by that planned value . please guide me i only calculate the planned value of that activity,

thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Shabbir,

If You desire that the cost planned in the network activity does not reduce the budget (assigned values), in the your Network type Tcode OPSC does not set the indicator "planning".

Regards

Elza

shabbir_ahmed2
Explorer
0 Kudos

Thanks Elza Aparecuda da silva this solve my problem

Answers (0)