on 03-01-2007 1:04 PM
HI ALL
when i planned the network activity cost in project system then system also assigned that amount against the budget ....so my avable budget is reduce by that planned value . please guide me i only calculate the planned value of that activity,
thanks
Dear Shabbir,
If You desire that the cost planned in the network activity does not reduce the budget (assigned values), in the your Network type Tcode OPSC does not set the indicator "planning".
Regards
Elza