On a Public Holiday scheduling was done for the planned order in a repetitive manufacturing?

0 Kudos

Dear Gurus,

There is a issue in my current scenario (REM mfg): In the quality server we check that one of the user is facing a issue after the run of MRP planned orders are generated. One of the planned order consider the Public holiday and give the finished date for the planned order.

So, i went and assigned the factory calendar in the work center and did the re-run of the MRP but still the result is same and system is considering the public holiday.

So, kindly please provide me any solution on this please...on ASAP....

Thanks & Regards,

Madhu. G

0 Kudos

any one can please provide me a help or clue what could be the reason on it...

Accepted Solutions (1)

Accepted Solutions (1)

0 Kudos

Hi All,

I got the solution, actually there is a issue with system upgraded with EHP 8 is working fine and without upgrade was not functioning properly so we are going to raise OSS note to SAP

Thanks & Regards,

Madhu. G