Hi Gurus,
I know there is no standard procedure to change back the status from REL to CRTD on project level. Still, our new business process requires that not every wbs element is released directly with creation....
For new projects we do not have a problem as we just won't release on project level. But we have a lot of old projects in status REL, thus new wbs elements would be released directly with creation.
We thought about a z-program which just changes the status directly in the table JEST for all concerned projects.
Do you see any problem about that?
Many thanks in advance!
Sandra