Dependent requirement from APO not transferred to ECC..

Former Member
0 Kudos

Hello Guys, We have dependent requirement for certain materials in APO which are planned in ECC but these are not getting transferred to ECC.

I am getting below Error in MD05 screen:

Error calculating the APO requirements for material W709729S442 / 4001

Message no. AUTO_CIF002

Diagnosis

An error occurred while determining the APO requirements for material W709729S442 / 4001 using RFC.

System Response

The system may not have been able to or only partially able to determine the APO requirements.

Procedure

Check the system settings. Possible causes are, for example:

  • Incorrect distribution of the master data, that is, the materials do not exist or are inconsistent in the APO System.
  • Error in the RFC link, that is, either the APO System or the RFC link is not available at present.

Check the connections to the RFC destination as necessary.

  • The liveCache is not available in the SAP APO system.

RFC is working fine and materials are also part of active IM.

Could you please suggest?