Dashboard content is not populated with Planned Cost and Actual Cost

Hi

We are working in cProjects 4.0 + ECC 6.0 implementation. I could not get the data for columns in Planned Cost and Actual Cost in cProjects Project Dashboard. I have properly mapped the config settings and created and assigned a Project in PS

Has anybody got this data in the Dashboard?

Kindly suggest the solution

with regards,

K Rama Krishna

9394712743

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Best Answer
    Posted on Feb 28, 2007 at 08:52 AM

    Hi,

    please take a look at note 1008546.

    Best regards.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 28, 2007 at 08:41 AM

    Hi Rama,

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Rama,

      It is difficult to say, where the problem is.

      but typically, the causes of the problem are

      customizing is set incorrectly or the evaluation is not carried out.

      You can run the the evaluation DPR_EVE_BATCH_DPO additionally, please untick the flag 'check the last changed date'.

      Hope, it helps.

      Kind regards,

      Zhenbo

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.