Hello:

From my understanding PDS= BOM+Routing/ Master receipe

I was wondering if I am integrating PDS into APO, is that enough. Do I still need to bring over the BOM or just PDS integration serve the purpose.

Thank you in advance.

Mono

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hai,

There won't be any BOM in APO. All you have is either PPM or PDS. Your BOM is part of PPM/PDS.

Former Member
0 Kudos

Hi Visu:

Thank you for the reply, I think my way I asked wasnt right. I am trying to create an Integration model for PDS and BOM, do I really need to create and activate a seperate integration model for BOM or just CIFing over PDS is enough.

Thanks

Mono

Former Member
0 Kudos

Hi

the PDS that are generated from R/3 master data contain data from BOM, Routing and Master recipe

You CIF the PDS and not BOM.