Scenario for procurement from MRP

All,

Please see the scenario :

Requirements of raw materials for procurement are coming through MRP.

Suppose MRP proposed a requirement for 15 March -07 for a material 'x' based on the planned delivery time .

The vendor doesn't supplied the material on 15th March -07 .

It will be supplied on 20th March-07.

Also please note MRP runs daily at midnight in background .

1. So how this will effect the MRP ?

2. Any changes should be made in the PO by procurement dept ?

Kindly advise.

regards

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Feb 27, 2007 at 05:10 AM

    Hi

    1. a. When the MRP is run on 15th, 16th upto 19th, the MRP list will show the item as pending PO i.e. the item is in pipeline.

    b. When the MRP is run on 20th, it will consider teh item as Stock

    2. If you want the MRP to reflect the exact delivery schedule, then you either have to change the delivery date or have Confirmation Control in PO Item detail. Here, you will have to fill the Expected date of delivery acknowledged by teh Vendor.

    However, if you only want that the MRP should consider the item as outstanding, then you need not make any changes to the PO.

    Hope this clarifies.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 26, 2007 at 07:11 PM

    Hi Sandeep,

    MRP scheduling is done per your settings in MRP2 view of material master, where u have given the planned delivery days. So system does the scheduling for 15march 07 as mentioned by ramki.

    regards

    Anand.C

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Feb 26, 2007 at 05:42 PM

    Hi Sandeep

    if you do not reflect that vendor is going to supply on 20 March 2007, then MRP still assumes that you would receive on 15th March and calculates the reqmts.

    If you update the date (either by changing PO, or by creating an inbound delivery with delivery date as 20 Mar 07), then system will correct the supply date as 20th in MD04. You will have more realistic picture of shortages/missing parts then.

    Best regards

    Ramki

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.