I have problem in closing a project. I receive an error CJ824

May 28, 2017 at 08:33 AM

69

avatar image
Former Member

Message no. CJ824

Diagnosis

While editing an asset in construction for the WBS element, an error occured.

System Response

Processing stopped.

Procedure

Go to the asset in construction for the WBS element and correct the error that appears there.

I have already seen some answers with regard to this . One of them being extend thee validity of the Cost center used in the project. I have a valid cost center.

Can some body still assist further

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Sunil Yadav May 29, 2017 at 06:02 AM
0

Hi Abhinav,

please check below link:

https://archive.sap.com/discussions/thread/3722150

according to suggession given by experts you can check if something pending with AUC:

also check :

https://archive.sap.com/discussions/thread/3284769

thanks

Sunil