Hi,

I have a scenario wherein the raw material is having base UOM as EA and issue unit as KG. Also the 30 KG= 1EA conversion is added. I the BOM for FG this material is in KG so the requirement calculated as per BOM is in KG but in the stock requirement list the requirement is generated as 1 EA even if the qty required is 1.2 KG. Unnecessary 30 KG i,e, 1 EA requirement is generated.. ANy suggestion for this scenario other than making Base unit of measure as KG ?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

3 Answers

swapnil rajane May 30, 2017 at 07:46 AM
1

Hi Anand,

Maintain the component UoM Kg in BOM of header material.

Regards.

Swapnil

Share
10 |10000 characters needed characters left characters exceeded
Solomon Macwan May 23, 2017 at 08:06 AM
0

Hi Anand,

I think the system is working correctly. you have maintain the unit EA, rather than you have to maintain unit PC

The difference between each an piece is that , in each you can not have the decimal places and in pieces you can have decimal places.

Have you maintain the production unit.

The best solution would be to change the base unit from EA to PC.

regards

Solomon

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Solomon,

Many thanks for addressing to the issue that I am facing. I have maintained issue unit and purchase order unit of measure both as KG. I agree to the point that I can make Base UOM as PC so that I can maintained it in decimals but this is not possible as business wont allow it. Another thing is that there is a conversion of 1 EA = 30 KG maintained. When I have a demand of only 1.2 KG suppose for this material still the PR of 1 EA is generated. Is there any other way, I can treat this so as to get the procurement proposal generated of the exact quantity as my demand.

Thanks

Anand

0
Solomon Macwan May 25, 2017 at 08:59 AM
0

Hi Anand,

As I said, the system is working correctly,

What you can do it that, in CUNI you can make the EA basu unit of measure with the decimal places.

Regards,

Solomon

Show 4 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Solomon,

Many thanks!!

I was just thinking on if there can be an enhancement done while creation of the requirement to club all the demand in KG and convert it into EA for ex. Plan order 1 = issue qty 1.2 KG, plann order 2 = issue qty 2 KG simillarly when there be plan order enough to equal 30 KG requirement then MRP should generate the procurement proposal for 1 EA.

What say on this ?

Thanks

Anand

0

Hi Anand,

Why do you need a enhancement? You just need to make the Unit with decimal places in Transaction CUNI.

Than the system will generate req as 1.500 pcs

or simply use the rounding value.

regards,

Solomon

0
Former Member
Solomon Macwan

Hi Solomon,

I have a restriction to not to change the BUOM or CUNI settings as well for the UOM EA or PC.

Is there any other way based on lot size or Reorder point planning to make sure exact requirement is generated or requirement is clubbed anyhow so as to prevent the excess qty proposal from getting generated ?

Thanks

Anand

0
Former Member
Solomon Macwan

The material which I am dealing with cannot be set with a BUOM as PC. Either KG or EA.

0