Fix planned order moved to anothe date

0 Kudos

Hi Team,

After fix the planned order in DS board , next day order gets move to another date

(future date or past date ). we could see such kind of behaviour for few orders only not for all. (MRP BJ running daily in ECC for non apo product)

.

Could you please advice on the same

?

Accepted Solutions (0)

Answers (1)

Answers (1)

yasmin_alayyan
Advisor
Advisor
0 Kudos

Hi Suren Bhelkar, how are you?

When we fix the order in DS Planning Board the same is marked as "date-fixed". After you notice it was date changed, was the order still fixed or not?

I have found this note, please check whether it is useful:

2335340 - 'Date Fixed' is reset after change in ECC

Best Regards.