Configure Approval of X need out of Y Direct Approvers

Hi Experts,

How do I configure Approvers for scenario Approval of X persone needed out of Y configured Direct approvers in SAP Business byDesign .

e.g.

Say for PO Approval I want to configure 3 direct approver But i want to define like any 2 of those 3 configured direct approval is Acceptable and can be moved to next steps ..

is it possible in SAP BYD to configure such scenario ? HOW ?

Regards,

Rakesh Mourya.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    May 22, 2017 at 04:58 PM

    using

    Skip Reapproval worked as expected and configured two steps with same approvers (3 Approvers but since we have two steps identical with

    Skip Reapproval Checked ) .. scenario 2 of 3 is achieved

    Add comment
    10|10000 characters needed characters exceeded

  • May 23, 2017 at 01:34 AM

    Hi Rakesh,

    Yes. Skip re-approval will work for your use case.

    Best Regards,