i had created a request for procurement. if the material is already exist then how the general store will issue the stock against that purchase request.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Govind Ramesh May 22, 2017 at 07:04 AM
0

Dear Joseph,

You can convert the Purchase request created to an STO (Stock Transport Order).

This STO should have the supplying plant as the General Store (Maintain Configuration)

Once the STO is converted to a picking list and delivery, then the Post Goods Issue of this delivery from general store will ensure the transfer of goods.

Regards,

Share
10 |10000 characters needed characters left characters exceeded
Jürgen L
May 22, 2017 at 07:36 AM
0

There is no goods issue in reference to a purchase requisition. You can have a goods issue to a reservation. If there is not enough quantity to fulfill a reservation then the MRP run might create a requisition to replenish the stock. Still you create a PO from the requisition, you receive against the PO and finally you goods issue against the reservation.

If you have enough stock then simply delete your requisition if it is not needed.