Hi Guys,
I am Copying actual data posted in 'X' cost center with version '0' to 'Y' cost center with version '1' through t-code KP98.
While copying I am selecting only Primary costs and Activity quantities.
I am able to execute the transaction witout any errors and it is giving a log that 'X' no. of records are copied, which is perfect.
But the problem is when I verify data in target cost center i.e. in 'Y' cost center it is showing some different values.
The target values are not reconciling with source values. It is copying activity quantities perfectly but actual costs it is giving some wrong values. I don't know from where it is getting those values.
Can any one help me in this?
Thanks
Ravi