Hello!

We have one material supplied by two vendors, Let's say Planned delivery time for One supplier deliver it in 10 days and other is in 1 days, thus average 5 days is maintained in the Material master.

Info record maintained for both suppliers, but when we create Quota arrangement, Planned delivery time is showing "Zero" for both suppliers. In quotas, Planed Delivery time is supposed to be weekly delivery on Thursdays.

Material master has Planned delivery time is 5 and planning calendar "004"(Delivery on Thursday) .

Appreciate if someone can shed some light why in the quotas planned delivery time is showing zero, or do we have to maintain manually in quotas, if so what can we maintain to tell the system for "weekly delivery on Thursdays"?

Thanks!

Cheers

Amit

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    May 22, 2017 at 03:48 PM

    you did not say what planned delivery time you maintained in your info records.

    The F1 help explains that a value can default from the VSR (vendor sub range) data of your vendor master

    Add comment
    10|10000 characters needed characters exceeded

  • May 22, 2017 at 03:18 PM

    planned-delivery-time.png

    Hello ,

    Little correction...Planned delivery date(time) :)

    Cheers

    Amit

    Add comment