Hi,

I am using ppds optimizer with bp. I see that soemtimes the optimizer schedules the planned orders that way, that they start before end of one block and end in the next block. but according to classification and block definition the planned orders should run only in one of the blocks...

I am playing with different optimizer settings but by now could not resolve the issue....

APO PPDS 7.0

thank you in advance for any hints.

kr,

Pilvi