Dear Sir,

We have a scenarios, Example A department is having 30 Activites to be performed during maintenance in diffrent cyle.

JAN 1 2 3 4 5 .........................

Act1 - 1M E1 E2

Act2 - 1M E1 E2

ACT3 - 3M E2

ACT4 - 3M E1

ACT5 - 6M E1

ACT6 - 6M

ACT7 - 9M

ACT8 - 9M E1

ACT9 - 9M E2

ACT10 - 9M E1 E2

FEB 1 2 3 4 5 .........................

Act1 - 1M E1 E2

Act2 - 1M E1 E2

ACT3 - 3M

ACT4 - 3M E2

ACT5 - 6M

ACT6 - 6M

ACT7 - 9M E1

ACT8 - 9M E2

ACT9 - 9M E1

ACT10 - 9M E2

Like this planning performed activiy wise. Based on this I am creating Plan. On a perticular day I am getting 13-20 Maintenance orders generated by the system. It looks very Cumbersome.

Please guide to make it single order for one equipment.